Administration and Policy Manual APM 4.5 Review of MOC |
Doc No.: APM 4.5 Revision: 0 Date: 15Apr 2023 Issued by: DPA Approved by: MD Page: 1 |
4.5 Review of MoC
4.5.1 General
- Document the changes sufficiently for its review
- Review the change to ensure:
- Progress monitored against time
- Objectives achieved
- Risks managed
- Any deviations are:
- Identified
- Addressed
- Any identified improvements to the plan are recorded
- They are working effectively / as designed
- Temporary changes do not exceed the initial authorization for:
- Scope
- Time
Note: If this happens, review and re-approve the change by the appropriate level of management.
4.5.2 When to Review MoC?
Office
At least quarterly during management meetings.
Ship
During handover of Masters and Chief Engineers.
Additional Review by Office or Ship
- The change has not been successful
- The proposed timescale has been exceeded
- Review the change
- Revalidate the change
- Approve the change